Replying to: History and Memories > Parent comment

Timeline:

Grace Universalist Church 1908 - 1937 (?)

  • Designed by Boston architect George F. Newton
  • Constructed: 1907-1908 Grace Universalist
  • Buffalo Sanitary Bulletin 2/28/1909: it was also used for basketball and public lectures

Studio Arena 1937 - 1969 (?)

Roderick L Griffis 1969 - 1978

  • 303 Lafayette purchased 11/26/1969

Charismatic Center 1978 - 2022

303 Lafayette LLC 2022 - present

  • purchased for $60,000 11/23/2022
  • mortgaged for $100,000 11/23/2022
  • "Big Reveal" on buffalorising.com: 2/06/2025
  • Signs posted: 2/07/2025
  • Zoning Board of Appeals 2/19/2025
  • Community meetings 3/07/2025
  • Planning Board (withdrawn) 3/10/2025
  • Developer meeting 3/12/2025
  • Developer meeting announced 6/17/2025 for the following Monday (for 6/23 at 6:30)
  • Developer meeting cancelled with 2:38 PM 6/23/2025
  • Developer meeting requested End of June (for 7/10 at 6)
  • sent to one neighbor who was out of town and received it 7/3/2025
Chris Nicolai
301 Lafayette
Reply
Developer meeting 7/10/2025 hoping to go before the Planning Board 7/28/2025 hoping to go before the Zoning Board of Appeals in September 2025 anticipating an 18 month time frame for construction
  • Developer meeting 7/10/2025
  • hoping to go before the Planning Board 7/28/2025
  • hoping to go before the Zoning Board of Appeals in September 2025
  • anticipating an 18 month time frame for construction
[parent]